BPVOY4 - "ALL INCLUSIVE" FREIGHT COVERING ALL COSTS OF VOYAGE - RIVER BERTH REQUIRING STANDBY TUGS
Afforded a range of ports within the fixture recap, Charterer directed the Vessel to a river berth wherein due to high current, standby tugs were required. Owner claimed the cost of the standby tugs from Charterer. Charterer pointed to freight being “ALL INCLUSIVE” and thus covering all costs of the voyage inclusive of standby tugs.
NYPE - INORDINATE AND INEXCUSABLE DELAY AFTER COMMENCEMENT OF ARBITRATION - ARBITRATION ACT OF 1996 - APPLICATION FOR DISMISSAL DUE TO WANT OF PROSECUTION - LIMITATION PERIOD - APPLICATION TO APPEAL TO HIGH COURT
Damage claims arose after the collapse of a crane on board a vessel. Arbitration commenced two years later however no submissions were made until nearly 12 years after the incident. Charterer applied to have the claim dismissed for want of prosecution by owner. The panel agreed with charterer and owner applied to the High Court for a chance to appeal.
VESSEL ORDERED TO ANCHOR OUTSIDE “PORT LIMITS” BY PORT AUTHORITY - DEFINITION OF “PORT LIMITS” - WHETHER VESSEL CONSIDERED GEOGRAPHICALLY READY TO TENDER NOR WITHIN THE CONTEXT OF C/P - DEMURRAGE
A vessel arrived off of the load port and was instructed by the port authority to anchor outside the port limits to await berth availability. The Court was tasked at determining whether the vessel was geographically ready for the purposes of tendering notice of readiness. The Court also looked at the definition of “port limits”.
DEMURRAGE - DETENTION - WHETHER VESSEL IN BREACH OF PUMP WARRANTY - WHETHER OWNER SHOULD BEAR EXTRA SHIFTING EXPENSES INCURRED WHEN THE VESSEL WAS ORDERED OFF THE DOCK DUE TO SLOW DISCHARGE - DELAY AWAITING DOCUMENTS AT DISPORT
Due to a slow discharge rate, the vessel was forced off her berth by port authorities. And after hoses disconnected at the disport, the vessel was delayed in departing for over 4 hours whilst awaiting documents onboard. Charterer denied Owner’s subsequent claims for demurrage, additional shifting expenses, and detention leading to this arbitration.
INTERIM PORT CALL FOR CUSTOMS REQUIREMENT BEFORE AND AFTER DISCHARGE - DEVIATION - BUNKER COSTS - DEMURRAGE
When the vessel was required to attend a port prior to and after the disport for customs reasons, owner charged the transit times from and to the interim port, the time in the interim port, and extra bunkers consumed. The charterer rejected owner’s claim under the auspices that the interim port calls were “beyond charterer’s control”.
CHARTER PARTY - SPECIFIC DISCHARGE PORT PROVISIONS - DEMURRAGE COP - DISPUTE OVER “ALWAYS ACCESSIBLE” PROVISION - DEMURRAGE AND DETENTION IN QUESTION
After the vessel arrived at the disport, a port strike coupled with low berthing priority status caused extensive delays. The owners argued that charterers had not met their responsibility of providing a berth that was “always accessible” and sought to claim reimbursement for this delay as detention, or alternatively, demurrage.
ASBATANKVOY - DEMURRAGE - NOR VALIDITY - EXPEDITE INSPECTION - SUBSTANTIAL READINESS – “ROOT CAUSE” PRINCIPLE
Nearly 38 days after the tender of NOR, charterer inspected and subsequently directed the vessel to repair its anchor chain prior to berthing. The repair took 3 days. Charterer subsequently claimed that as the vessel was not ready the NOR was invalid with the 38 days for Owner’s account.
DISPONENT OWNER TERMINATING TIME CHARTER FOR CHARTERER’S FAILURE TO PAY HIRE - WITHOUT PREJUDICE PRIVILEGE - WHETHER PARTIES IN DISPUTE - WHETHER OWNER WAIVED CHARTERER’S BREACH - IMPOSSIBILITY OF PERFORMANCE DEFENSE - MEASURE OF DAMAGES
With the subject vessel out on time charter disponent owner was not receiving hire from charterer. As funds were not passed from disponent owner to head owner, head owner terminated the head charter and disponent owner in turn cancelled the charter with charterer. The panel was tasked at determining whether prior settlement discussions between the parties should be admissible or protected by privilege. Further, the panel would need to determine whether owner had waived charterer’s breaches and then whether or not to award damages.
BIMCO OREVOY VOYAGE CHARTER - VESSEL UNABLE TO LIFT MINIMUM QUANTITY - OWNER CLAIMS FORCE MAJEURE - CHARTERER REPUDIATES CHARTER AND CHARTERS SUBSTITUTE VESSEL
A vessel arrived at the load port with a portion of her previous cargo frozen to the inside of her hold. After owner failed to secure a substitute vessel charterer terminated the charter and fixed its own sub. Charterer’s claim for damages was denied by owner who presented a counterclaim basis what owner believed to be charterer’s wrongful repudiation of the charter party.
NYPE 1993 TIME CHARTERS - FAILURE TO PAY HIRE - WITHDRAWAL OF VESSEL FROM LONG TERM TIME CHARTER - WHETHER PUNCTUAL HIRE PAYMENTS A CONDITION OF THE CHARTER - WHETHER CHARTERER IN RENUNCIATORY BREACH
While on separate time charters owner withdrew three vessels from service due to charterer’s failure to pay hire in accordance with the contracts. Owner brought arbitration against the charterer. However, shortly before the hearing the charterer was liquified and the proceedings stayed. The present case involves the charterer’s parent company, as guarantor.