Interchem 2000 Logistics BV v. Suffolk Tankers Co., Ltd. (The “Rachel B”) – SMA No. 4150, 9 Dec 2011

ASBATANKVOY -- VESSEL BREAKDOWN -- ENGINE PROBLEM -- SEAWORTHINESS -- Owner Award At the time of the fixture, Vessel was in drydock for repairs. After undocking further repairs were found to be required subsequently causing the Vessel to miss her laydays. Charterer cancelled the fixture incurring costs in finding a suitable replacement which Charterer is claiming from Owner in this arbitration.